Question 33:
You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won`t affect your project much if they happen. What should you do with these identified risk events?
Answer options:
A. These risks can be accepted. B. These risks can be added to a low priority risk watch list. C. All risks must have a valid, documented risk response. D. These risks can be dismissed.