Question 38:

You are the project manager for your organization. You have identified a risk event youre your organization could manage internally or externally. If you manage the event internally it will cost your project $578,000 and an additional $12,000 per month the solution is in use. A vendor can manage the risk event for you. The vendor will charge $550,000 and $14,500 per month that the solution is in use. How many months will you need to use the solution to pay for the internal solution in comparison to the vendor`s solution? 

Answer options:

A. Approximately 13 months
B. Approximately 11 months
C. Approximately 15 months
D. Approximately 8 months