Question 73:

You and your project team are just starting the risk identification activities for a project that is scheduled to last for 18 months. Your project team has already identified a long list of risks that need to be analyzed. How often should you and the project team do risk identification? 

Answer options:

A. At least once per month
B. Identify risks is an iterative process.
C. It depends on how many risks are initially identified.
D. Several times until the project moves into execution