Question 55:
You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project`s schedule performance index?
Answer options:
A. 1.06 B. 0.92 C. -$37,800 D. 0.93