Question 144:
Fred is the project manager of the CPS project. He is working with his project team to prioritize the identified risks within the CPS project. He and the team are prioritizing risks for further analysis or action by assessing and combining the risks probability of occurrence and impact. What process is Fred completing?
Answer options:
A. Risk identification B. Risk Breakdown Structure creation C. Perform qualitative analysis D. Perform quantitative analysis