Question 34:

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response 

Answer options:

A. Project sponsor
B. Risk owner
C. Diane
D. Subject matter expert