Question 23:
You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:
How much capital should the project set aside for the risk contingency reserve?
Answer options:
A. $142,000 B. $232,000 C. $41,750 D. $23,750