Question 23:

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: 
image
How much capital should the project set aside for the risk contingency reserve? 

Answer options:

A. $142,000
B. $232,000
C. $41,750
D. $23,750