Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric`s organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric`s organization liable to pay the ZAS Corporation for the work they have completed so far on the project? 

Answer options:

A. Yes, the ZAS Corporation did not choose to terminate the contract work.
B. It depends on what the outcome of a lawsuit will determine.
C. It depends on what the termination clause of the contract stipulates.
D. No, the ZAS Corporation did not complete all of the work.