Question 1682:
Management considered two projections for its business continuity plan; plan A with two months to recover and plan B with eight months to recover. The recovery objectives are the same in both plans. It is reasonable to expect that plan B projected higher:
Answer options:
A. downtime costs. B. resumption costs. C. recovery costs. D. walkthrough costs.