Question 232:
While reviewing the project plan for a new system prior to go-live, an IS auditor notes that the project team has not documented a fallback plan. Which of the following would be the BEST go-live approach in this situation?
Answer options:
A. Parallel processing B. Immediate cutover C. Real-time replication D. Load balancing