Question 401:

What is the BEST strategy to prioritize work when planning a follow-up audit? 

Answer options:

A. Target risks that are most easily mitigated.
B. Agree on priorities with risk owners.
C. Target the areas of highest risk.
D. Target risks not reported as mitigated by risk owners.