Spreadsheets are used to calculate project cost estimates. Totals for each cost category are then keyed into the job-costing system. What is the BEST control to ensure that data are accurately entered into the system?
Answer options:
A. Reasonableness checks for each cost type B. Validity checks, preventing entry of character data C. Display back of project detail after entry D. Reconciliation of total amounts by project