Question 79:
Which of the following is the MOST appropriate responsibility of an IS auditor involved in a data center renovation project?
Answer options:
A. Performing independent reviews of responsible parties engaged in the project B. Ensuring the project progresses as scheduled and milestones are achieved C. Performing day-to-day activities to ensure the successful completion of the project D. Providing sign off on the design of controls for the data center