Question 92:

An IS auditor is conducting a pre-implementation review to determine a new system`s production readiness. The auditor`s PRIMARY concern should be whether: 

Answer options:

A. the project adhered to the budget and target date
B. users were involved in the quality assurance (QA) testing
C. there are unresolved high-risk items
D. benefits realization has been evidenced