Question 445:
An IS auditor noted that a change to a critical calculation was placed into the production environment without being tested. Which of the following is the BEST way to obtain assurance that the calculation functions correctly?
Answer options:
A. Check regular execution of the calculation batch job B. Perform substantive testing using computer-assisted audit techniques (CAATs) C. Obtain post-change approval from management D. Interview the lead system developer