Question 675:

In assessing the priority given to systems covered in an organization`s business continuity plan (BCP), an IS auditor should FIRST: 

Answer options:

A. review results of previous business continuity plan (BCP) tests.
B. review the backup and restore processes.
C. verify the criteria for disaster recovery site selection.
D. validate the recovery time objectives and recovery point objectives.