Question 101:

You are the risk official of your enterprise. You have just completed risk analysis process. You noticed that the risk level associated with your project is less than risk tolerance level of your enterprise. Which of following is the MOST likely action you should take? 

Answer options:

A. Apply risk response
B. Update risk register
C. No action
D. Prioritize risk response options