Question 11:
You are the project manager of GHT project. Your project team is in the process of identifying project risks on your current project. The team has the option to use all of the following tools and techniques to diagram some of these potential risks EXCEPT for which one?
Answer options:
A. Process flowchart B. Ishikawa diagram C. Influence diagram D. Decision tree diagram