Question 114:
You are working as the project manager of the ABS project. The project is for establishing a computer network in a school premises. During the project execution, the school management asks to make the campus Wi-Fi enabled. You know that this may impact the project adversely. You have discussed the change request with other stakeholders. What will be your NEXT step?
Answer options:
A. Update project management plan. B. Issue a change request. C. Analyze the impact. D. Update risk management plan.