Question 133:

You are the project manager of HGT project. You have identified project risks and applied appropriate response for its mitigation. You noticed a risk generated as a result of applying response. What this resulting risk is known as? 

Answer options:

A. Pure risk
B. Secondary risk
C. Response risk
D. High risk