Question 143:
You are completing the qualitative risk analysis process with your project team and are relying on the risk management plan to help you determine the budget, schedule for risk management, and risk categories. You discover that the risk categories have not been created. When the risk categories should have been created?
Answer options:
A. Define scope process B. Risk identification process C. Plan risk management process D. Create work breakdown structure process