Question 154:

You are the project manager of GHT project. You have applied certain control to prevent the unauthorized changes in your project. Which of the following control you would have applied for this purpose? 

Answer options:

A. Personnel security control
B. Access control
C. Configuration management control
D. Physical and environment protection control