Question 158:

You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response? 

Answer options:

A. Risk register
B. Risk log
C. Project management plan
D. Risk management plan