ExamQuestions.com

Register
Login
Certified in Risk and Information Systems Control Exam Questions

Isaca

Certified in Risk and Information Systems Control

163 / 500

Question 163:

You are the project manager of GHT project. You have initiated the project and conducted the feasibility study. What result would you get after conducting feasibility study? Each correct answer represents a complete solution. (Choose two.) 

Answer options:

A. Recommend alternatives and course of action
B. Risk response plan
C. Project management plan
D. Results of criteria analyzed, like costs, benefits, risk, resources required and organizational impact