Question 17:
You are an experienced Project Manager that has been entrusted with a project to develop a machine which produces auto components. You have scheduled meetings with the project team and the key stakeholders to identify the risks for your project. Which of the following is a key output of this process?
Answer options:
A. Risk Register B. Risk Management Plan C. Risk Breakdown Structure D. Risk Categories