Question 176:

Beth is a project team member on the JHG Project. Beth has added extra features to the project and this has introduced new risks to the project work. The project manager of the JHG project elects to remove the features Beth has added. The process of removing the extra features to remove the risks is called what? 

Answer options:

A. Detective control
B. Preventive control
C. Corrective control
D. Scope creep