Question 198:

Judy has identified a risk event in her project that will have a high probability and a high impact. Based on the requirements of the project, Judy has asked to change the project scope to remove the associated requirement and the associated risk. What type of risk response is this? 

Answer options:

A. Exploit
B. Not a risk response, but a change request
C. Avoidance
D. Transference