Question 211:

You are the project manager for Bluewell Inc. You are studying the documentation of project plan. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channel s for the project? 

Answer options:

A. 20
B. 100
C. 50
D. 300