Question 217:
Shawn is the project manager of the HWT project. In this project Shawn`s team reports that they have found a way to complete the project work cheaply than what was originally estimated earlier. The project team presents a new software that will help to automate the project work. While the software and the associated training costs $25,000 it will save the project nearly $65,000 in total costs. Shawn agrees to the software and changes the project management plan accordingly. What type of risk response had been used by him?
Answer options:
A. Avoiding B. Accepting C. Exploiting D. Enhancing