Question 258:

You are the project manager of the PFO project. You are working with your project team members and two subject matter experts to assess the identified risk events in the project. Which of the following approaches is the best to assess the risk events in the project? 

Answer options:

A. Interviews or meetings
B. Determination of the true cost of the risk event
C. Probability and Impact Matrix
D. Root cause analysis