Question 26:
You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders` approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase?
Answer options:
A. Human resource needs B. Quality control concerns C. Costs D. Risks