Question 269:
You are the project manager of GHT project. You have analyzed the risk and applied appropriate controls. In turn, you got residual risk as a result of this. Residual risk can be used to determine which of the following?
Answer options:
A. Status of enterprise`s risk B. Appropriate controls to be applied next C. The area that requires more control D. Whether the benefits of such controls outweigh the costs