Question 277:

You are the project manager of GHT project. You identified a risk of noncompliance with regulations due to missing of a number of relatively simple procedures. The response requires creating the missing procedures and implementing them. In which of the following risk response prioritization should this case be categorized? 

Answer options:

A. Business case to be made
B. Quick win
C. Risk avoidance
D. Deferrals