Question 298:
Adrian is a project manager for a new project using a technology that has recently been released and there`s relatively little information about the technology. Initial testing of the technology makes the use of it look promising, but there`s still uncertainty as to the longevity and reliability of the technology. Adrian wants to consider the technology factors a risk for her project. Where should she document the risks associated with this technology so she can track the risk status and responses?
Answer options:
A. Project scope statement B. Project charter C. Risk low-level watch list D. Risk register