298 / 500

Question 298:

Adrian is a project manager for a new project using a technology that has recently been released and there`s relatively little information about the technology. Initial testing of the technology makes the use of it look promising, but there`s still uncertainty as to the longevity and reliability of the technology. Adrian wants to consider the technology factors a risk for her project. Where should she document the risks associated with this technology so she can track the risk status and responses? 

Answer options:

A. Project scope statement
B. Project charter
C. Risk low-level watch list
D. Risk register