Question 3:

You are the project manager of GHT project. You have identified a risk event on your project that could save $100,000 in project costs if it occurs. Which of the following statements BEST describes this risk event? 

Answer options:

A. This risk event should be mitigated to take advantage of the savings.
B. This is a risk event that should be accepted because the rewards outweigh the threat to the project.
C. This risk event should be avoided to take full advantage of the potential savings.
D. This risk event is an opportunity to the project and should be exploited.