Question 304:

You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification process? 

Answer options:

A. Quality management plan
B. Stakeholder register
C. Cost management plan
D. Procurement management plan