Question 311:
A project team member has just identified a new project risk. The risk event is determined to have significant impact but a low probability in the project. Should the risk event happen it`ll cause the project to be delayed by three weeks, which will cause new risk in the project. What should the project manager do with the risk event?
Answer options:
A. Add the identified risk to a quality control management chart. B. Add the identified risk to the issues log. C. Add the identified risk to the risk register. D. Add the identified risk to the low-level risk watch-list.