Question 314:

You are preparing to complete the quantitative risk analysis process with your project team and several subject matter experts. You gather the necessary inputs including the project`s cost management plan. Why is it necessary to include the project`s cost management plan in the preparation for the quantitative risk analysis process? 

Answer options:

A. The project`s cost management plan provides control that may help determine the structure for quantitative analysis of the budget.
B. The project`s cost management plan can help you to determine what the total cost of the project is allowed to be.
C. The project`s cost management plan provides direction on how costs may be changed due to identified risks.
D. The project`s cost management plan is not an input to the quantitative risk analysis process.