Question 321:

You are the project manager of GHT project. A stakeholder of this project requested a change request in this project. What are your responsibilities as the project manager that you should do in order to approve this change request? Each correct answer represents a complete solution. Choose two. 

Answer options:

A. Archive copies of all change requests in the project file.
B. Evaluate the change request on behalf of the sponsor
C. Judge the impact of each change request on project activities, schedule and budget.
D. Formally accept the updated project plan