Question 326:

Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has introduced a scope change request for additional deliverables as part of the project work. What component of the change control system would review the proposed changes` impact on the features and functions of the project`s product? 

Answer options:

A. Cost change control system
B. Configuration management system
C. Scope change control system
D. Integrated change control