Question 333:

You are the project manager for your organization to install new workstations, servers, and cabling throughout a new building, where your company will be moving into. The vendor for the project informs you that the cost of the cabling has increased due to some reason. This new cost will cause the cost of your project to increase by nearly eight percent. What change control system should the costs be entered into for review? 

Answer options:

A. Cost change control system
B. Contract change control system
C. Scope change control system
D. Only changes to the project scope should pass through a change control system.