Question 367:

You are the program manager for your organization and you are working with Alice, a project manager in her program. Alice calls you and insists you to add a change to program scope. You agree for that the change. What must Alice do to move forward with her change request? 

Answer options:

A. Add the change to the program scope herself, as she is a project manager
B. Create a change request charter justifying the change request
C. Document the change request in a change request form.
D. Add the change request to the scope and complete integrated change control