Question 38:

You are the project manager of the HGT project in Bluewell Inc. The project has an asset valued at $125,000 and is subjected to an exposure factor of 25 percent. What will be the Single Loss Expectancy of this project? 

Answer options:

A. $ 125,025
B. $ 31,250
C. $ 5,000
D. $ 3,125,000