Question 401:

A program manager has completed an unsuccessful disaster recovery test. Which of the following should the risk practitioner recommend as the NEXT course of action? 

Answer options:

A. Identify what additional controls are needed
B. Update the business impact analysis (BIA)
C. Prioritize issues noted during the testing window
D. Communicate test results to management