Question 438:
When reviewing a business continuity plan (BCP), which of the following would be the MOST significant deficiency?
Answer options:
A. BCP is often tested using the walkthrough method B. BCP testing is not in conjunction with the disaster recovery plan (DRP) C. Each business location has separate, inconsistent BCPs D. Recovery time objectives (RTOs) do not meet business requirements