Question 47:

John works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk? 

Answer options:

A. Activity duration estimates
B. Activity cost estimates
C. Risk management plan
D. Schedule management plan