Question 51:
You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won`t affect your project much if they happen. What should you do with these identified risk events?
Answer options:
A. These risks can be dismissed. B. These risks can be accepted. C. These risks can be added to a low priority risk watch list. D. All risks must have a valid, documented risk response.