Question 62:

You are the project manager of RFT project. You have identified a risk that the enterprise`s IT system and application landscape is so complex that, within a few years, extending capacity will become difficult and maintaining software will become very expensive. To overcome this risk, the response adopted is re- architecture of the existing system and purchase of new integrated system. In which of the following risk prioritization options would this case be categorized? 

Answer options:

A. Deferrals
B. Quick win
C. Business case to be made
D. Contagious risk