Question 71:

Which of the following processes addresses the risks by their priorities, schedules the project management plan as required, and inserts resources and activities into the budget? 

Answer options:

A. Monitor and Control Risk
B. Plan risk response
C. Identify Risks
D. Qualitative Risk Analysis