Question 89:
The only output of qualitative risk analysis is risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?
Answer options:
A. Trends in qualitative risk analysis B. Risk probability-impact matrix C. Risks grouped by categories D. Watchlist of low-priority risks